Current Status

Progress status as on
01st Sept 2024

Excavation: 946/953

PCC: 941/953

Raft: 940/953

Shear Wall: 935/953

Grade Slab: 882/953

Ground Floor Slab: 875/953

First Floor Slab: 870/953

Terrace Floor Slab: 862/953

Water proofing: 348/953

Internal putty: 157/953

Internal - Tiling (flooring/dado): 69/953

External – Texture: 47/953

External – 1st coat Painting: 42/953

Internal-1st coat painting: 4/953