Current Status

Progress status as on
01st Sept 2024

Excavation: 369/437

PCC: 359/437

Raft: 348/437

Columns upto Plinth: 305/437

Grade Slab: 43/437

Ground Floor Slab: 36/437

First Floor Slab: 30/437

Terrace Floor Slab: 25/437